The Wates team and our sub-contractors would like to thank you for your continued patience whilst we have been on site at Centenary Way. Our site will close for the Christmas period on Tuesday 24 December, and will re-open in the New Year on Thursday 2 January. Can we also take this opportunity to wish you a Merry Christmas and a Happy New Year! Friday, 29 November 2013. Friday, 25 October 2013. Friday, 11 October 2013. Externally this week the bricklayers and renderers complete.
Tuesday, 25 June 2013. Friday, 21 June 2013. Wednesday, 10 April 2013. Wednesday, 20 February 2013. Progress has been slow in January due to the adverse weather and cold temperatures, however Febr.
We have come a long way since the blog has been down. With only weeks to go before handover the internal are almost complete. As you can see with the photos, the first and second floor are complete, only leaving the main entrance corridor to decorate. We are having the final push on the externals and the temporary car park being replaced back to the original state before we arrived. Monday, 22 July 2013. Friday, 5 July 2013. Friday, 21 June 2013. The second phase of External Wo.
Mass concrete works have been completed to the retaining wall and the facing stonework has been laid ready for coping stones. Kerbing and hard landscaping works are progressing to the front of Block 1 and adjacent to Block 2. Friday, 21 June 2013. Excavations ,steel fixing and concrete pour for the retaining wall are now completed. As trench is now excavated and g. As, water and electric are now connected to all plots. Monday, 22 April 2013. Monday, 8 April 2013.