Friday, 23 August 2013. Externally British Gas laid the mains and fitted the meters. Northern power grid have commenced on site pulling the mains cable and next week will connect onto the existing services. Internally much the same as last week 2nd fix electrics fitting lights and sockets. Plumbers are connecting the sinks and fitting the showers in blocks 2 and 3, giving the plots a feel of completion with only the final decoration to do. Friday, 16 August 2013.
Work on site is now complete and it is ready to handover. Friday, 21 June 2013. The subcontractors are pressing on with the internals with the first and second fix of the mechanical and electrical fittings, this allows for the joiners to fit the kitchens. Monday, 17 June 2013. The rainwater harvesting tank has been installed this week, it will be used to store rainwater collected from the roofs and then supply this water to the ground floor properties for flushing toilets.
Now the tarmac has been laid the site looks complete. All that remains to be done is the planting and the snagging. Internally Kirklees Council are undertaking their final inspections before the planned handover date of February 13th. Monday, 23 December 2013. Can we also take this opportunity to wish you a Merry Christmas and a Happy New Year! Friday, 20 December 2013. All remains is to wish you all a Merry Christmas and a Happy New Year from all the site staff.
Monday, 23 December 2013. The Wates team and our sub-contractors would like to thank you for your continued patience whilst we have been on site at Sampson Grange. Our site will close for the Christmas period on Tuesday 24 December, and will re-open in the New Year on Thursday 2 January. Can we also take this opportunity to wish you a Merry Christmas and a Happy New Year! Friday, 4 October 2013. Monday, 2 September 2013. Friday, 5 July 2013. Friday, 28 June 2013.
External Works are progressing well here at Sandy Mount. Due to the lack of space on site the site management have had to meticulously create a sequenced programme which would allow the ground workers to work from the rear of the site to the front. The team here at Sandy Mount are confident that the external works will continue without hindrance and be complete in line with the programme. Wednesday, 22 January 2014. Monday, 6 January 2014. Monday, 23 December 2013.